For homebuyers in Maharashtra, the introduction of the Real Estate (Regulation and Development) Act, 2016 fundamentally changed how project delays are handled.
While many discussions casually refer to “Rule 15” when talking about extensions, the legal foundation for extending a real estate project’s completion timeline actually lies in Section 6 and Section 7(3) of the Act.
If you’ve invested in an under-construction property, understanding these provisions is critical.
Under Section 6, a real estate project’s registration may be extended only in cases of force majeure.
The Act defines force majeure as events such as:
For example, during the COVID-19 pandemic, many state authorities including Maharashtra Real Estate Regulatory Authority granted blanket or case-specific extensions treating the pandemic as force majeure.
Important:
Market slowdown, poor sales, or financial mismanagement are not considered force majeure under Section 6.
Section 7 primarily deals with extension of the proposed completion date of the registered project by receiving consent to do so by more than half of the allottees.
However, Section 7(3) allows the Authority, instead of revoking registration immediately, to:
In practical terms, if a promoter defaults but revocation would harm allottees, the Authority may allow continuation under strict supervision rather than canceling the project outright.
This protects buyer interests and prevents abandoned projects.
In Maharashtra practice, when promoters seek extension (especially beyond force majeure grounds), they are generally required to:
This ensures developers cannot unilaterally extend timelines without stakeholder approval.
Here’s how it typically works:
If granted, the revised completion timeline is updated on the project’s MahaRERA webpage.
You Have Legal Protection
The promoter cannot indefinitely delay possession without regulatory scrutiny.
Force Majeure Is Limited
Only genuine uncontrollable events qualify under Section 6.
You Can Exit
If the delay becomes unreasonable, Section 18 allows buyers to seek a refund with interest.
Authority Can Step In
Under Section 7(3), MahaRERA may intervene to safeguard project completion rather than let it collapse.
Before RERA, project delays often stretched for years with little accountability.
Post-RERA:
Sections 6 and 7(3) collectively ensure that extensions are structured, conditional, and transparent, rather than arbitrary.
When you hear about “project extension under RERA,” remember:
Understanding this distinction gives you clarity and leverage as a homebuyer.